How Long Does It Take to Finish a Basement?

What is the timeline for a finished basement? Learn more about the typical basement finishing timeline and what the longest phases are.

If you are wondering how long it takes to finish a basement, there are many factors to consider. The first step you should take is finding a contractor. A contractor can help give you the most accurate timeline of your finished basement project. An average custom finished basement project usually ranges anywhere from 12-16 weeks. The plans for your specific basement remodel could be reflected in the timeline.

How Are Finished Basement Timelines Scheduled?

So you met with a contractor and came up with a plan and proposal, now the real fun begins! Once all the pre-work is done and the basement is ready, the basement transformation begins. 

  • Deliver Rough Materials: 1 day
  • Framing: Can be completed anywhere from 5-7 days
  • Rough installation of electrical and plumbing: Can be completed in 5-7 days
  • Rough Inspections: 3-5 day
  • Install Insulation: 1 day
  • Putting up Drywall: 10-14 days
  • Finish and Prime Drywall: 2-3 days
  • Doors and Trim Delivery: 1 day
  • Installing trim: 5-7 days
  • Set Cabinets: 1-4 days
  • Ceiling Grid: 2-4 days
  • Spotting: 2 days
  • First Painting: 2-4 days
  • Install Tile: 2-4 days
  • Install countertops: 1 day
  • Flooring Installation: 4-6 days
  • Final Mechanicals: 2-3 days
  • Second Spotting: 2-5 days
  • Second Painting: 2-4 days
  • Carpet Install: 2 days
  • Finishing touch-ups: 2-5 days
  • Final inspections: 2-5 days
  • Punchout: 3 days
  • Final Cleaning: 1 day

Is There Anything that can Cause a Timeline Extension?

Although there is a general overview of how long the basement finishing timeline is, life happens, and delays can too. If you have a larger space, framing that space can take longer than the allotted 5-7 days. If any issues arise with plumbing and/or electrical, this can also cause a delay. Another thing to consider is the inspections. Inspections take 1 day but it could take a couple of days for the inspector to make it out to the job site. Obviously, the larger the basement, the longer the project will take but generally, contractors can give you a very good estimate.

The Benefits of Finishing a Basement Professionally

There are many benefits to finishing a basement professionally Should you hire a professional or DIY your Basement Finishing Project? (finishedbasementsplus.com) . Basement professionals and contractors have a clear vision and know what to expect when it comes to a remodeling a basement. They are aware of potential setbacks and know how to handle any delays that may arise. When you are given a timeline by a professional, you should expect the work to follow very closely. 

Let Us Help You Define Your Basement Finishing Timeline  

Having a finished basement timeline can put your mind at ease. At Basement Plus we can help bring your vision to life in a timely and professional manner. Contact us today for a free consultation Contact – Basements Plus (finishedbasementsplus.com)

 